--- title: "Construction Work in Progress (WIP) Adjustments" slug: "construction-work-in-progress-wip-adjustments" tags: ["Language - English", "Area - Reporting", "Area - Scheduling", "Industry - Construction", "Type - Reference", "Role - Branch Manager", "Role - Operations Manager", "Role - System Admin", "Role - Branch Admin", "Skill Level - 2 (Intermediate)"] updated: 2025-12-15T22:18:59Z published: 2025-12-15T22:18:59Z canonical: "guide.youraspire.com/construction-work-in-progress-wip-adjustments" --- > ## Documentation Index > Fetch the complete documentation index at: https://guide.youraspire.com/llms.txt > Use this file to discover all available pages before exploring further. # Construction Work in Progress (WIP) Adjustments ## **Purpose** The purpose of this article is to explain what a Construction WIP (Work in Progress) adjustment is and how to complete one in Aspire. ## **What is a Construction WIP Adjustment?** A Construction WIP Adjustment allows you to adjust the **Projected Cost to Complete** and **Projected Gross Margin** displayed on the Job Dashboard. This gives Project Managers a clearer view of how a project is performing and how revised cost expectations may affect profitability. A WIP Adjustment updates the financial projection values on the Job Dashboard. It does **not** change the estimated values on individual work tickets or modify the original estimate, including any change orders. Before making a WIP Adjustment, your Job Dashboard may look like this: ![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-81imr46b.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=g5YU97SX28DwLKKQlk2XIctkqrzzHUFSC1u5hVfj3G4%3D) Note:The **Estimated Cost** and the **Projected Cost****to Complete** are the same. After making an adjustment, the Job Dashboard may look like this: ![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-biuzac79.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=45YDJw6fyAjfdCUyph1YIomBEHkS891LXygu%2BIx6yeg%3D) Note: The **Estimated Cost** and **Projected Cost to Complete** now differ, and the **Projected Gross Margin** has been updated. ## **How to make a Construction WIP Adjustment** 1. Make sure the Opportunity’s **End Date** is not in the past. Opportunities with a past end date will not display in the Construction WIP Adjustment list. 2. Go to **Reports > Standard Reports** and select **Construction WIP Adjustments** under the Production category.![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-pmednluw.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=LD1Ov2VYmmCU43Lr%2BqXpwMIcar%2BGcG3J1KgFF%2B7AE8E%3D) 3. Locate the Opportunity you want to update (for example, Opportunity #6837). 4. Select the **more actions (⋯)** menu on the right and choose **Edit Cost to Complete**.![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-71odozs5.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=dUFAr6qLTTUP7W2H3aesPb7z%2Bh2V3Pn9QE13MU4lz7Q%3D) 5. This opens a list of all work tickets associated with the opportunity.![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-s5xvb6t5.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=lukwcdmQHY5AEKQWRew0oYeLU5t6B8LrH4JfW9F1DzM%3D) 6. Enter the revised **Cost to Complete** value for each work ticket you want to adjust.![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-ixuvprc4.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=c2bdg20ShySLXQlZgxAlVvmKi8KOTetiXj9vVwidk6E%3D) 7. Confirm your changes and select **Save**. Once saved, return to the Opportunity’s Job Dashboard to review the updated **Projected Cost to Complete**, **Projected Profit**, and **Projected Gross Margin**. Note:The original **Estimated Cost** remains unchanged so you can monitor how the job is trending over time. ![](https://cdn.document360.io/5942a8d7-f3b1-4919-bdfa-d477d8498fe3/Images/Documentation/construction-work-in-progress-wip-adjustments-image-4qclg6f2.png?sv=2026-02-06&spr=https&st=2026-11-17T00%3A31%3A42Z&se=2026-11-17T01%3A31%3A42Z&sr=b&sp=r&sig=FakWpgeRMgtoOCXkE6rdwufeNJ3R9mfeYVEPGThrtlQ%3D) ## **How Construction WIP Adjustments Appear in Reports** Construction WIP Adjustment values are included in the **Work in Progress (Work Orders) report**. This ensures consistency between the Project Manager’s Job Dashboard and your financial reporting. The following fields in the Work in Progress report reflect WIP adjustments: - **Job Status** - **Projected Cost to Complete** These fields allow you to track adjusted cost projections alongside committed costs and revenue expectations.