- 16 Jan 2023
- Print
- PDF
Job Dashboard Summary
- Updated on 16 Jan 2023
- Print
- PDF
The following table summarizes the elements of the main screen of the Job Dashboard.
Element | Description |
---|---|
Profitability Info Section – This section | |
Original Contract | Original estimated amount for the work order. |
Change Orders | Total estimated amount for all change orders associated with the work order. |
Current Contract | Original estimated amount plus amounts of all change orders. |
Estimated Cost | Contract estimated price with changes. Clicking this value will drill down into the Job Dashboard Cost Drill Down Report. |
Estimated GM % | Estimated GM Dollars / Current Contract |
Estimated GM Dollars | Contract estimated price (with changes) less the estimated cost. |
Projected Cost to Complete | Currently projected cost accounting for changes from estimates that are specified using the Construction WIP Adjustments Report. Clicking this value will drill down into the Job Dashboard Cost Drill Down Report. |
Projected GM % | Projected GM Dollars / Current Contract |
Projected GM $ | This is the sum of the most recent cost to complete entries (if they exist) as specified from the WIP Adjustments Report for the tickets on the opportunity if they exist. If no cost to complete entries have been made for a ticket, shows the total estimated cost. |
Cost to Date % | Cost to Date Dollars / Estimated Cost |
Cost to Date $ | Sum of accepted costs (Labor, Material, Equipment, Sub, Other) on the opportunity. Costs are accepted from the Time Entry screen or by receiving associated purchase receipts to work tickets (excluding receipt to job inventory). Clicking this value will drill down into the Job Dashboard Cost Drill Down Report. |
Billed to Date % | Billed to Date Dollars / Current Contract |
Billed to Date Dollars | Amount invoiced to date. Clicking this value will drill down into the Job Dashboard Invoices Drill Down Report. |
Gross Margin % | Cost to Date / Billed to Date |
Gross Margin Dollars | Billed to Date less Cost to Date. |
Earned Revenue (%) | Earned Revenue / Current Contract |
Earned Revenue ($) | Calculated based on standard Earned Revenue calculation for Aspire. |
Graph | |
Graph: Estimated Cost | A bar showing the estimated cost for the opportunity. |
Graph: Actual Cost | A bar showing the actual cost for the opportunity to date. |
Graph: Projected Cost | Bar showing currently projected cost that accounts for changes from the original estimate that have been specified using the Construction WIP Adjustments Report. |
Graph: Contract | |
Cash Positions Section – This section | |
Billed to Date | Amount invoiced for the job to date. Clicking this value will drill down into the Job Dashboard Invoices Drill Down Report. |
Less Open A/R | Amount remaining to be paid on the invoice. Clicking this value will drill down into the Job Dashboard Invoices Drill Down Report. |
Less Retention | Retainage that has been set aside based on created invoices, but not yet invoiced. Clicking this value will drill down into the Job Dashboard Retainage Drill Down Report. |
Cash In | Total payments and credits for the job. |
Cost to Date | Cost recognized to date on the job. Sum of the values for Labor Expense and A/P Direct Cost fields underneath Cost to Date. |
Labor Expense | Displays actual labor cost to date for the job. Clicking on this item displays the Job Dashboard Costs Search List screen to provide additional detail. |
A/P Direct Cost | Displays total cost for the job minus labor costs. Clicking on this item displays the Job Dashboard Costs Search List screen to provide additional detail. |
Job Inventory | Displays the dollar amount of items that have been purchased to job inventory but have not yet been applied to the job. Clicking on this item displays the Job Inventory Costs Search List screen to provide additional detail. |
Less Open A/P | Cost of items on purchase receipts that have been received but not approved. Clicking this value will drill down to the Job Dashboard Receipt Drill Down Report. |
Less Committed | Cost of items on purchase receipts that have not been received. |
Cash Out | Cost that has been approved for payment. (Cost to Date - (Less Open AP + Less Committed)) |
Cash Flow | Shows the net cash received for the job - the difference between payments received for the job and cost incurred. (Cash In – Cash Out) |
Dials | Dials showing projected profit and cash flow. |
Job Dashboard Cost Drill Down Report
The Job Dashboard Cost Drill Down Report is implemented as an advanced search list that shows the cost associated with all work tickets for the selected job. This drill-down report is displayed by clicking the following hyperlinks in the Job Dashboard:
- Estimated Cost in Profitability Info Section
- Projected Cost in Profitability Info Section
- Cost to Date in Profitability Info Section
This search list makes the following fields available.
- Work Ticket Number
- Service Name
- Estimated Total Cost
- Actual Total Cost
- Projected Total Cost
- Estimated Labor Cost
- Actual Labor Cost
- Estimated Material Cost
- Actual Material Cost
- Estimated Sub Cost
- Actual Sub Cost
- Estimated Equipment Cost
- Actual Equipment Cost
- Estimated Other Cost
- Actual Other Cost
Job Dashboard Invoices Drill Down Report
The Job Dashboard Invoices Drill Down Report is implemented as an advanced search list that provides information for all invoices associated with the selected job. This drill-down report is displayed by clicking the following hyperlinks in the Job Dashboard:
- Billed to Date in Profitability Info Section
- Billed to Date in Cash Position Section
- Less Open A/Rin Cash Position Section
This search list makes the following fields available.
- Invoice Number
- Invoice Date
- Invoice Type
- Invoice Amount
- State Tax Amount
- Federal Tax Amount
- Amount Remaining
- Invoice Batch Status
Job Dashboard Retainage Drill Down Report
For Open Billing work orders, The Job Dashboard Retainage Drill Down Report is implemented as an advanced search list that provides information for all retainage information for invoices associated with the selected job. This drill-down report is displayed by clicking the following hyperlinks in the Job Dashboard:
Less Retainage in Cash Position Section
This search list makes the following fields available.
- Invoice Number
- Invoice Date
- Retainage Amount
Job Dashboard Receipt Drill Down Report
The Job Dashboard Receipt Drill Down Report is implemented as an advanced search list that provides information for all purchase receipts associated with the selected job. This drill-down report is displayed by clicking the following hyperlinks in the Job Dashboard:
- Less Open A/P in Cash Position Section
- Less Committed in Cash Position Section
This search list makes the following fields available.
- Receipt Number
- Vendor
- Status
- Received Date
- Approved Date
- Vendor Invoice Date
- Vendor Invoice Number
- Opportunity Receipt Cost
Job Dashboard Costs Search List Screen
Clicking on Labor Expense or A/P Direct Cost in the Cash Position section displays the Job Dashboard Costs Search List screen which shows the work tickets and associated costs for the job as depicted below:
You can drill-down further into any of the work tickets displayed in the list for additional detail.
Job Inventory Costs Search List Screen
Clicking on Job Inventory in the Cash Position section displays the Job Inventory Costs Search List screen (labeled Job Dashboard Costs) which shows allocations to job inventory based on purchase (positive cost) and allocations from job inventory to the job (negative cost), as depicted below:
You cannot drill-down further into these line items.